Recent events indicate that Eskom should concentrate on generating power and leave new build projects to professional project managers. The Medupi power station is two years late for a number of reasons, a major contributor being the boiler protection software which is part of the plant’s control and instrumentation system, and which keeps failing Eskom’s acceptance tests, but which should have been handed over to the utility in December 2012… (more)